Camfaud special projects team successfully deliver another complex project

1 min reading time

Camfaud special project team completed a complex pipeline pour Saturday night/Sunday day at Liverpool Street Station. The project involved installing a riser and 200m pipeline to pump 75m3 on platform 2/3 in partial station closure. Using our ECOPAN with blow out lid we were able to safetly clear the line with compressed air.

Camfaud provided:

  • Autocad work for design of riser

  • RAMS for pipeline and pump set up

  • 2 x Shifts with PTS/TVP support

  • HIAB for moving and collection of ecopans leaving no waste concrete on site from the hopper, pipeline and pipe wash facility.

Bring on the next phase in a few weeks time!

Big thanks to the team who attended site and planned the works.